VBBL Part 11 Upgrade Trigger Assessment (preliminary screen)
Step 1 · Building basics
How many storeys is the existing building?
Building area
The area of the largest storey (footprint), per the By-law definition of building area.
Step 2 · The change of major occupancy
Is the change confined to a single suite?
A suite is a single room or series of rooms operated by one tenant or owner. If the whole building is one tenancy, the suite can be 100% of the building.
Area changing major occupancy in this project (same units as above)
Area of any OTHER changes of major occupancy in this building in the past 5 years (0 if none)
The 5 year limit is cumulative and includes the current work (Note 2 to Flow Chart No. 2).
Approximate area of construction work for this project
Used only for the 100 m² single-suite exception in Sentence 11.5.4.1.(1)(a), which also requires the work to not exceed 5% of the building area. If unsure, enter the change area.
Step 3 · Existing and proposed occupancies
Existing (last permitted) major occupancy and use
Proposed major occupancy and use
Hazard index values are transcribed from Tables A-11.2.1.2.-C and A-11.2.1.2.-D of the City's Notes to Part 11 (unofficial wording effective Jan 1, 2023). The value depends on whether the aggregate area is 200 m² or less, or more than 200 m²; the tool applies the band automatically from your change area. Confirm values for your project.
Hazard index handling
Step 4 · Occupant load and heritage
Current occupant load (entire building, persons)
Proposed occupant load (entire building, persons)
Occupant loads are determined under Subsection 3.1.17 of Division B. The change may be assessed comparatively considering only the areas changing occupancy (per the notes to Flow Chart No. 2).
Would the required upgrades conflict with an approved heritage retention plan?
RESULT
How this result was reached
Advisory notes
Inputs used
Preliminary screen only. The Chief Building Official makes the final determination of project classification, occupancy classification, hazard index, occupant load and upgrade levels. Where a project scope includes multiple categories of work, the highest upgrade level in each category shall apply and include the requirements of all lower upgrade levels. Structural note: where structural load paths or structural design criteria are altered, it must be demonstrated that the existing building has the structural capacity to carry the increase in load, or the building shall be structurally upgraded to carry the increase in live load (notes to Flow Chart No. 2).
Sources: 2025 Vancouver Building By-law, By-law No. 14343 (in force Sept 15, 2025), Part 11, incl. Article 11.5.1.2 (Required Upgrade Levels), Article 11.5.2.1 (Upgrade Trigger Mechanism, Flow Charts No. 1 and 3) and Article 11.5.4.1 (Special Cases, Flow Chart No. 2);
Section 11.5 unofficial wording (Sept 15, 2025);
Notes to Part 11 incl. Hazard Index Tables (Jan 1, 2023);
City of Vancouver, Building By-law page.